Dongfeng Dana Axle Xiangfan Factory Nissan Innovation High

From February 9th to 14th, Dongfeng Dynamo Axle of Xiangfan Factory produced more than 800 axles per day. The progress of the entire rear axle assembly steadily progressed. Staff of the entire factory grabbed high-yielding opportunities and won a good new year for Wuzi.

In January, the front axle and rear axle assembly completed by the Dongfeng Dana Axle's Xiangfan factory increased by 52% and 31% respectively over the same period of last year. In February, the front and rear axle assembly of the plant planned to produce 17,840 units, and the production task set a record high. The start of the new high-yield production greatly encouraged the morale of the cadres of the entire plant. In order to ensure the successful completion of the high-yield task in February, the Xiangfan plant was well-prepared before the Spring Festival. The plant did a good job in equipment maintenance, especially in the antifreeze work of equipment and facilities; all units carried out post-holiday production mobilization in depth, and completed the ideological work of employees in advance. At the beginning of the first month of April, the cadres and staff of the factory put into intense production work. Some workshops even began production on the middle and night shifts on the third day of the third year.

Faced with high output, the plant further tapped potential. The production department, on the one hand, ensures that resources are available in a timely manner. On the one hand, it strengthens management assessment to ensure the smooth completion of the Nissan plan. The production workshop actively overcomes the power shortage problem, carefully organizes and makes full use of low valley power production. The workshop and the workshop are more than full-blown and the night shift starts a labor competition. The production capacity of the axle assembly and components has been greatly improved. .